Construction Change Directive vs Change Order

A change order records an agreed change. A construction change directive can direct work before price or time is fully agreed, when the governing contract permits it.

The distinction matters because the contractor's obligation, the required signatures, and the path to a final price depend on the signed contract. Under commonly used AIA documents, a directive keeps work moving while cost or time remains unresolved; an executed change order records the parties' agreement.

Open prefilled generator

Check authority before treating an instruction as approval

A field request, email, or architect comment is not automatically the same as a contract-authorized directive. Identify who may direct changes, how notice must be delivered, and whether the contractor must proceed before price agreement.

Price and track unresolved work separately

Record the directed scope, date, labor, materials, equipment, subcontractor cost, and schedule effect. Keep agreed and disputed amounts distinct so the project record does not imply an agreement that has not occurred.

Close the loop with the contract's final instrument

When scope, cost, and time are resolved, use the document required by the contract to record the agreement. Under the referenced AIA workflow, resolved directive work is incorporated into a change order.

Decision table

Directive or agreed change?

QuestionChange directiveChange order
AgreementPrice or time may remain unresolvedScope, price, and time are agreed
Typical purposeDirect timely work under the contractRecord the parties' approved modification
Contractor responseProceed or respond as the contract requiresPerform the mutually authorized change
Cost recordTrack actual and proposed adjustmentState the agreed adjustment
CloseoutResolve and incorporate per the contractBecomes the signed modification record

Next step

Put the workflow into practice

CO-001

Hidden-condition document path

Example
Condition
Damaged roof decking is uncovered during tear-off and delays dry-in.
Direction
The authorized project representative directs replacement within the contract's change procedure before final quantity is known.
Daily record
The contractor records sheets, labor, disposal, photos, notice, and schedule effect by date.
Resolution
The parties agree on final quantity, price, and one additional day.
Final record
The resolved adjustment is documented using the signed change instrument required by the contract.

What this example covers

Confirm which change mechanism the signed contract authorizes
Separate agreed amounts from disputed or not-yet-priced work
Document notice, direction, labor, materials, and schedule effects
Convert resolved directive work into the contract's final change record

More field paperwork

Related contractor guides

Primary references

Check the governing documents

These references explain common document workflows. Your signed contract and applicable law control your project.

Important note

This is practical paperwork guidance, not legal advice. Review important construction documents with qualified counsel before use.