Field guide

Change Order for Remodeling

Create a remodeling change order for owner upgrades, added fixtures, or changed finishes.

Remodeling jobs change often because clients see new options once work starts. A change order keeps the upgrade separate from the original scope and makes cost approval clear.

Open prefilled generator

Anchor the change to the original room scope

Identify the room, drawing, allowance, or estimate line being changed. A clear reference separates the upgrade from work already included in the contract price.

List labor, materials, and finish work

State fixture quantities, model or allowance assumptions, wiring or plumbing work, drywall repair, paint touch-up, and anything the owner will supply.

Record selection and schedule dependencies

Name the date selections are due and explain whether special-order materials or inspections add time. Get approval before ordering or opening finished surfaces.

CO-001

Completed remodeling change order example

Example
Original scope
Replace the kitchen cabinets and reconnect the six existing light fixtures.
Owner request
Add four recessed LED lights and relocate two switch boxes before drywall patching.
Included work
Fixtures, wire, boxes, electrician labor, permit allowance, drywall patches, and one coat of touch-up paint.
Added cost
$1,240 added to the contract; decorative fixtures remain owner-supplied.
Schedule
Two work days added if fixture selections are approved by August 3.
Approval
Owner approval required before electrical rough-in begins.

What this example covers

Added fixture or finish description
Materials and labor included
Excluded hidden electrical or wall conditions
Added cost and timeline impact

More field paperwork

Related contractor guides

Important note

This is practical paperwork guidance, not legal advice. Review important construction documents with qualified counsel before use.